Please view and download individual PDF files as needed for reference.
Before • Courthouse Buildings to be Removed
During Demolition
After Removal of Buildings
3 - 3
<
>
Demolition of the Circuit Court in Norfolk consisted of demolishing 102,500 square feet of the two story building in Downtown, including the steel framed underground basement. Heavy Demolition included recycling over 95% of deconstructed materials. Select Demolition required “soft” stripping the entire building, with complete removal of all materials throughout the structure that were not made of metal, brick, or concrete. Abatement included all friable and non-friable PCB, mercury, and asbestos. Over 3,715 tons of concrete were recycled. The building was less than 60 feet from City Hall, which remained open and active throughout demolition, with no interruptions.
Download PDF of Norfolk Circuit Court
Before • Eight story building implosion.
During • Eight story building implosion.
After • Eight story building implosion.
3 - 3
<
>
Download PDF of Lincoln Park Implosion
Eight Story Building Down in Fifteen Seconds
The job required an explosive detonated demolition of an 8 story apartment complex, including 19 additional apartment and community buildings, on a 20 acre site. The implosion of the larger mid-rise building comprised 94,000 square feet of demolition and clearing. This particular implosion was the first ever in the City of Hampton VA. All the materials remaining on site after the implosion and heavy demolition were recycled, paving the way for redevelopment of the property.
Beginning demolition of Building 811.
Demolition further along.
Completion of Building 811 demolition.
1 - 3
<
>
Download PDF of Dormitory Demolition at Ft. Eustis
Lot Restored to Pristine Ground
An older dormitory was cleared for a repurposed area. This 3 story concrete structure served as barracks for members of the United States Army. It was located less than 100 feet away from another occupied barracks that frequently had troops active outside for training. Select demolition and abatement crews worked to strip the building of all non-recyclable, and asbestos containing materials in order for the heavy demolition to be successful in its process. The project was finished safely and on time.
Before • Larchmont Elementary School ready for heavy demolition.
During • Work well underway; rubble readied for processing.
After • School is competely demolished, ground leveled.
2 - 3
<
>
Download PDF of Larchmont Elementary School
Old School Replaced by New
Under pressure of new school opening in the adjacent lot, the demolition of the old Larchmont Elementary school included demolition, removal and disposal of approximately 78,000 SF of a three story school building. Prior to demolition, The 88 year old structure required asbestos abatement, PCB's, and materials containing mercury. Regulated abatement was required in conjunction with the demolition. The project was completed ahead of time, saving hundreds of man hours and weeks off the schedule. Meticulous segregation of non-contaminated materials still allowed over 90% to be recycled.
Before • Preparation in very tight quarters
During • Demolition Underway
After • Lot clear, ready for new construction
1 - 3
<
>
Download PDF of General District Court
Precision Demolition by New Courthouse
The Norfolk General District Court demolition required precise deconstruction of an area of structure, which was tightly situated between the General Safety Building and the new General District Courts building, with only a 6" clearance. Built in 1960, the 52,000 SF steel framed, reinforced concrete structure required careful select demolition of a 2 1/2 story building. Demolition was successfully achieved with no damage to either building. Safety Building stayed in operation with no interruptions due to demo activities. Over 95%, or 2000+ tons of demolished materials were recycled. Abatement included all PCB & mercury, friable and non-friable asbestos, insulation, mastic, and window glazing. Abatement took 2,200 man hours to implement, and was completed on time.
Before • Lynnhaven Parking Ramp Demolition
During • Lynnhaven Parking Ramp Demolition
After • Building clear, and graded for new parking
3 - 3
<
>
This job selectively deconstructed 89,000 square feet of a two-story parking garage, processing over 5,000 cubic yards of concrete. Concrete reinforced columns were removed, with 99% of the concrete (3,500 cubic yards) being crushed and processed on site for reuse. 5000 tons of recycled material was used as the underlayment for the new parking long. The entire scope of the work was performed while the mall stayed open, with no interruptions to mall services throughout the entire job.
Download PDF of Lynnhaven Mall Parking Ramp
All demolition processes accessed only by water!
Station before demolition, where heavy equipment was to operate.
Removal of demolition materials by barge.
Job completed. Area of demolition returned to pristine condition.
2 - 4
<
>
HEAVY DEMOLITION of Hog Island Coast Guard Station required transporting all heavy equipment and labor to the island on water by barge. After completion, all materials and debris was again removed by barge, leaving the coastline in a restored, environmentally pristine state.
Download PDF of Hog Island CG Station
Download PDF of Meadowbrook School
Download PDF of Campostella Elementary, ostensible progress.
Download PDF of SETC Training Center Job Profile
Download PDF of Old Cinemark Theater
Download PDF of Hatteras Coast Guard Station
Download PDF of Historic Seagull Inn demolition.
Download PDF of Mitsubishi Building
Download PDF of DePaul Job Profile
Download PDF of NASA Job Profile
Download PDF - Lynnhaven Mall Job Profile
Download PDF of Golden Sands Job Profile
Download PDF of Thrun Barracks Job Profile
Download PDF of Student Center Profile
Download PDF, Great Neck School Job Profile
Download PDF of Kempsville Rec Center Job Profile
Download PDF of Crossroads Elementary
Download PDF of Gwaltney Plant Job Profile
Download PDF of US Army P513 Barracks
Download PDF of Smithfield Foods Plant
Download PDF of CMC Rebar Building
Download PDF of Old Holiday Inn
Download PDF of Midtown Tunnel Bridge
Download PDF of Yorktown Victory Center
HEAVY DEMOLITION of the existing 46,000 square foot structure was completed, after full abatement of all friable materials was completed. In close proximity to the surrounding neighborhood Macsons crews worked with minimal interruption to residents. Twenty mature trees were preserved, buildings were demolished and over 75% of the materials were recycled, keeping them out of area landfills. Macsons completed every aspect of the project with trained in-house workers.
Demolition of Campostella Elementary was more constructive, in that it paved the way for developing a school twice the size of the one it replaced, and with a state of the art facility. The project included removal and disposal of approximately 94,700 sq. ft. of a one-story school along with the site demolition of 63,400 sq. ft. within the property. Abatement, demolition, and site demolition were conducted in a timely manner, as the schedule met all contractual performance goals. All concrete, brick and block building materials were crushed on site, in-house by Macsons. Over 8,000 tons of crushed materials were recycled, half of which were directly reused on site.
Aside from demolition and abatement, grading to current standards were the objective for this job. The project consisted of abating and demolishing buildings in the Eastern Virginia Training Center in Chesapeake. Additionally, selective roadways, parking lots and walkways were demolished and converted to green space. The site was backfilled according to mandated storm water regulations. Prior to demolition, all mercury bulbs, PCB light ballasts were abated, in addition to all category II asbestos containing floor tile and mastic. Over 95% of the buildings was recycled. The property was fine graded and seeded to restore pristine conditions.
The scope of this work consisted of the demolition, removal, and disposal of the building structure including all slabs and foundations, followed by back fill and grading of the site. A one and a half story, 27,000 Sf former movie theater was successfully demolished, along with all concrete materials, slabs, foundations, curbs, and sidewalks. Macsons recycled over 95% of the old theater.
This was the demolition of an entire Coast Guard Station, including 22 buildings. The job entailed the removal of asbestos and Haz Mat containing materials, all buildings, a pool, site features and associated utilities. The final phase restored the site to green space and beach access parking for the community.
The historic Seagull Hotel located at the Virginia Beach Oceanfront was taken down in very close quarters to neighboring active hotels, on one side--ten feet! Pedestrian safety and site cleanness were imperative. The inn was a 5 story concrete structure, covered in EFIS (stucco.) Working against strong winds, the surface had to be removed by hand, bagged, and lowered by boom lift to prevent flying debris from littering surrounding streets. Three buildings, including the Seagull Inn, the Seaside Inn next to it, and a Dairy Queen between them, were razed successfully.
This project included demolition, removal, and disposal of approximately 74,000 SF of a 3.5 story industrial ink toner plant. Prior to demolition, Macsons hand-washed 64,000 square feet of the plant to remove flammable toner dust. Over 3 miles of piping, structural steel, and the entire slab was cleaned, water collected in holding tanks, and removed from the site following strict EPA and state storm water pollution and prevention guide lines.
Demolition, hauling and disposal of the Vincent Building at DePaul Medical Center, immediately adjacent to active hospital areas. An estimated 98% of the building debris was retrieved and recycled on site by Macsons as the foundation for the new Doctors Parking Lot, also implemented by Macsons. After abatement and selective demolition of interiors, the five story building was collapsed within minutes, making way for new construction several months later.
HEAVY DEMOLITION of multiple buildings and launch-pad facility as well as removal of asbestos and protection of active NASA Space Station communication lines running through crawl space of buildings selected for demolition. Job required disconnect of all electrical and cooling systems, site work, along with backfill and landscaping.
HEAVY & SELECT DEMOLITION required removal of over 152,000 square feet of materials in both heavy and selective demolition, with no interruption of open stores, including increased consumer traffic from the opening of the Apple store, and introduction of iPhone 6.
HEAVY DEMOLITION for this project included demolition, removal, and disposal of approximately 5,300 square feet of a 3 story hotel, and an additional 25,000 square feet of a five story hotel at the oceanfront in Virginia Beach. The project also entailed the removal and disposal of non-friable asbestos materials, and off-site recycling of concrete block, brick, and asphalt into crushed stone. The project was successfully completed in a safe manner on Atlantic Avenue at the Virginia Beach Oceanfront, which is directly adjacent to the famous Virginia Beach Boardwalk.
HEAVY DEMOLITION: Structural demolition was pre-engineered and taken down in four coordinated controlled collapses, all in one day. The building itself was within 150ft of an active military flight line, no interruptions to the air field ever occurred. 95% of all building components were recycled creating over 12,000 tons of reusable product. Macsons performed the work 100% in-house to include the abatement, demolition, and crushing operation.
HEAVY DEMOLITION: This project consisted of heavy and select demolition of a former bowling alley, credit union, theater, science center and student dorms. Also, asbestos, lead & PCB removal, disposal and backfill was required. The work was executed safely and without issue while the campus remained open to the public during ongoing classes.
HEAVY DEMOLITION: The scope of work for this project included demolition, removal and disposal of approximately 110,060 sq ft of a two story school. Additionally, the project entailed removal and disposal of non-friable asbestos, as well as PCB contaminated materials. All concrete materials were salvaged and crushed on-site for reuse.
HEAVY DEMOLITION: The scope of work for this project included demolition, removal, and disposal of approximately 74,000 SF of a three story recreation center. Prior to demolition, friable and non-friable asbestos materials were removed. Along with the demolition and abatement activities, over 93%, (equating to approximately 11,000 tons) of the building materials being were recycled. All Concrete, brick, block, and asphalt materials were crushed on site, with the majority of these materials being reused on site, during the construction of the new recreation center.
HEAVY DEMOLITION of existing school building and recreation center. The work included removal of the school building, all pavement and ground structures and fixtures. Site Clearing included all shrubs and trees; asbestos abatement, PCB removal, mercury light fixtures, and contaminated soil.
The Gwaltney meat manufacturing plant project, in Portsmouth VA, consisted of the heavy demolition of 137,000 square feet of steel framed structure, in two stories. Abatement required safe removal of PCB mercury, Freon gas, and materials containing friable and non-friable asbestos. Deconstruction included crushing and recycling of 13,000 tons of concrete for use on site, 9,000 cubic yards of concrete was processed to 21 A/B spec material. Over 850 tons of metal was separated, removed and recycled. For completion, the entire site was rough graded for future new construction.
HEAVY DEMOLITION of Buildings 532, 533 and site involved HAZMAT demolition, remediation, and disposal of asbestos, lead, PCB's and mercury; and soil to a depth of 18" below building footprints. Slabs, foundations, and pile caps were demolished. Site demolition saw-cut and removed asphalt, concrete, curbs and timber piles. Debris was for the most part entirely recycled.
HEAVY DEMOLITION included asbestos abatement and disposal; in manifested loads, followed by demolition of the existing Smithfield Packing South Plant. Demolished areas were backfilled back up to grade with select fill, compacted in 1" lifts to 95% compaction. Four inches (4") of topsoil and seeding of the entire area completed the job.
Exterior Asbestos Panels Removed Prior to Demolition
PROJECT required abatement removal and disposal of friable and non-friable materials, followed by complete heavy demolition of the building. Four men with boom lifts executed the work one panel at a time. Heavy demolition removed and disposed of three warehouses and an office building totaling 64,074 square feet.
HEAVY DEMOLITION Asbestos abatement, PCB/Mercury removal and demolition of four and five story hotel structures. Demolition included over 87,500 SF of building structures, the removal of 8,400 SF of asphalt. Recycling created over 15,000 tons of re-usable products from debris. Macsons performed the work 100% in house, restoring the former building site to green space.
HEAVY DEMOLITION for this project required demolition of a retired railroad bridge overpassing the eastern mouth of the Norfolk Midtown Tunnel to be implemented in a one weekend closure. The work area was restricted to the 22’ limited access road bed, with the bridge being 16' above grade. Two excavators were used, utilizing special processors, hammers, and buckets. All materials were moved and recycled in Macsons crushing yard.
Demolition Includes Crushing & Recycling
HEAVY DEMOLITION of these buildings was a two-phase project, including the demolition of Welcome Center Theater and the Maintenance Garage. Macsons demolished 57,700 sf of a 3 story Museum, completing the job in 15 weeks, with 4 excavators, and an average 6 man crew. All brick, block, and concrete were crushed on site to fill the existing site for future use. The project was completed during activities and tours of the new museum and its grounds, less than 100yds away.
HOME | AWARDS & ANNOUNCEMENTS | COMMUNITY SERVICE | EMPLOYMENT | SERVICES | TESTIMONIALS